Question:medium

Arrange the following steps for applying the critical path method in the correct sequence :
A. Identification of all activities that the project require.
B. Network Diagram Construction
C. Critical Path Determination
D. Activity Duration Estimation
Choose the correct answer from the options given below :

Show Hint

Any delay in an activity on the "Critical Path" will directly result in a delay of the entire project completion date.
Updated On: May 20, 2026
  • A, D, B, C
  • A, B, D, C
  • D, A, B, C
  • B, A, D, C
Show Solution

The Correct Option is B

Solution and Explanation