Question:medium

A is thrice as efficient as B. Working together, they complete the work in 3 days. If working alone, B takes 8 days more than A to finish the whole work. What is the number of days taken by A to finish the whole work alone?

Updated On: May 6, 2026
  • \(6\)
  • \(4\)
  • \(8\)
  • \(12\)
  • \(10\)
Show Solution

The Correct Option is B

Solution and Explanation

Step 1: Understanding the Question:
The question requires us to calculate the exact number of days person A would take to complete a task entirely alone.
We are given two major conditions.
First, A is three times as efficient as B, and together they can finish the work in exactly 3 days.
Second, if they were to work individually, B would take 8 days more than A to complete the same work.
Step 2: Key Formula or Approach:
Efficiency is defined as the amount of work done per unit of time and is inversely proportional to the time taken.
If the efficiency ratio of A to B is $3:1$, the time taken ratio of A to B will be $1:3$.
Total work can be calculated as the product of total combined efficiency and the total time taken together.
Step 3: Detailed Explanation:

Let us assume the efficiency of worker B is $x$ units of work per day.

Since A is thrice as efficient as B, the efficiency of worker A will be $3x$ units per day.

When A and B work together, their combined efficiency is the sum of their individual efficiencies.

Combined efficiency = $3x + x = 4x$ units per day.

We are given that they finish the whole work together in exactly 3 days.

Total work can be found by multiplying their combined efficiency by the number of days they worked together.

Total work = $4x \text{ units/day} \times 3 \text{ days} = 12x$ units.

Now, we must find the time taken by A alone to finish this total work.

Time taken by A alone = $\frac{\text{Total Work}}{\text{Efficiency of A}}$.

Time taken by A = $\frac{12x}{3x} = 4$ days.

To verify our answer, we can check the secondary condition given in the problem.

Time taken by B alone = $\frac{12x}{x} = 12$ days.

The difference in their times is $12 - 4 = 8$ days.

This matches the problem's statement that B takes 8 days more than A perfectly.

Thus, A takes 4 days to finish the work alone.

Step 4: Final Answer:
The number of days taken by A to finish the whole work alone is 4.
Was this answer helpful?
0