Question:medium

A can complete a work in 12 days and B in 18 days. In how many days will they complete the work together?

Show Hint

For two people, you can use the formula: $\text{Time} = \frac{xy}{x+y}$. In this case: $\frac{12 \times 18}{12 + 18} = \frac{216}{30} = 7.2$.
Updated On: May 13, 2026
  • 6 days
  • 7.2 days
  • 8 days
  • 9 days
Show Solution

The Correct Option is B

Solution and Explanation

Was this answer helpful?
0


Questions Asked in CUET (UG) exam