Question:hard

A bord and pillar panel has 24 developed pillars of size \(40\ \text{m} \times 40\ \text{m}\) (centre to centre) under extraction. The following information is given:
Gallery width = \(4\ \text{m}\)
Extraction height = \(3\ \text{m}\)
Extraction ratio during depillaring = 80%
Specific gravity of coal = 1.4
Incubation period = 6 months
Average working days per month = 25
In order to extract the panel within the incubation period, the minimum rate of production, in tonne per day, is . (rounded off to one decimal place)

Show Hint

Work out the true size of each pillar once the gallery width is taken out of the centre to centre spacing, then think about how much coal that leaves to recover within the given incubation period.
Updated On: Aug 17, 2026
Show Solution

Correct Answer: 696.7

Solution and Explanation

Let's approach this by first working out the tonnage locked up in a single pillar, then scaling up to the whole panel, rather than totalling the volume first.

Each pillar's centre to centre spacing is 40 m, but 4 m of that on each pillar's boundary belongs to the surrounding gallery, so the actual coal pillar left standing is $40-4=36\ \text{m}$ on a side.

Volume of coal in one pillar $= 36 \times 36 \times 3 = 3888\ \text{m}^3$, using the 3 m extraction height.

During depillaring only 80% of a pillar's coal is actually recovered, so the recoverable volume per pillar is $0.8 \times 3888 = 3110.4\ \text{m}^3$.

At a specific gravity of 1.4, the mass recoverable from one pillar is $3110.4 \times 1.4 = 4354.56$ tonnes.

With 24 pillars in the panel, the total coal to be extracted is $24 \times 4354.56 = 104509.44$ tonnes.

The incubation period gives the time limit: $6$ months at $25$ working days a month is $150$ days. So the panel must be cleared at a rate of at least $104509.44/150 = 696.7296$ tonne per day.

Let's summarize:

  • Subtracting the gallery width from the centre to centre spacing gives the true pillar size of 36 m by 36 m.
  • Only 80% of a pillar's coal is won during depillaring.
  • Scaling one pillar's recoverable tonnage up to 24 pillars and dividing by the 150 available days gives the same minimum rate.

So the panel needs a minimum production rate of about $696.7$ tonne per day.

Was this answer helpful?
0