Consider the aggregate planning problem for a toy car manufacturing organization whose demand at a plant is as follows:

MonthSeptemberOctoberNovemberDecember
Demand (in units)80006500105009500

The organization has ONLY the following options available for aggregate planning to meet the demand: (1) in-house production, (2) subcontracting, and (3) inventory holding. Assume that the quantity subcontracted in a given month is available in the same month.

A part of their optimal solution is as follows:
Inventory at the end of October = 1500 units
Units produced in-house in November = 8000 units
Units subcontracted in November = 1000 units

The inventory at the end of November is ______ units (in integer).
  • GATE PI - 2026
  • GATE PI
  • Industrial Engineering
  • Aggregate production planning