Match List-I with List-II.

List-IList-II
A. Dummy activity
B. Critical path
C. PERT activity
D. Critical Path Method
I. Follow B distribution
II. Built on activity oriented diagram
III. Constructed only to establish sequence
IV. Has zero total slack

  • CUET (PG) - 2026
  • CUET (PG)
  • Mechanical Engineering
  • Project Management
If 'A' is the optimistic time, 'B' is the pessimistic time and 'C' is the most likely time of an activity, then the expected time of activity is:
  • CUET (PG) - 2025
  • CUET (PG)
  • Mechanical Engineering
  • Project Management
Arrange the following elements of a feedback control loop in the correct order: (A) Actuator (B) Error detection (C) Controller (D) Feedback sensor Choose the correct answer from the options given below:
  • CUET (PG) - 2025
  • CUET (PG)
  • Mechanical Engineering
  • Project Management
contact us
terms & conditions
Privacy & Policy
© 2026 Patronum Web Private Limited